Dermody

Louisville, KY

This particular tilt wall building had to be constructed on a 5’ slope due to unique site conditions. The foundations, slab-on-grade, and tilt wall construction were completed in less than two months. The site conditions would normally double the duration of a project for most construction teams. Our teams not only met the time requirements, but exceeded the floor flatness specifications and tilt wall tolerances for the project.


Project Specifications

  • 546,000 SF
  • $4,000,000 Budget
  • Tilt Wall with 5′ Slope due to Site Conditions
  • Completed in under 2 months while still exceeding requirements